Excavation for the new septic system underway




Monday, August 3

The site for the new building is now fully-cleared of demolition debris and the exact location of the new building has been staked out by the surveyors. Unfortunately, but not surprisingly, there is ledge all along the front foundation wall and other spots as well. The site contractor will excavate for the footings and we will be able to see exactly what we are dealing with. In some instances we may be able to pin the new foundation to the rock. In other instances, it will likely need to be removed.

Whichever way we go, it will need to be resolved this week, as we plan to begin pouring the footings and foundations early next week!

The new septic system is under construction as well.