Blasting was completed in the two required locations on Friday, and the week began by clearing the rubble. Forms were subsequently set for the footings. The necessary inspections have been conducted and the footings were poured on all but the front of the building. Footings will be complete by the end of the week. Foundations should be poured early next week.
The photos show the excavation for the footings and foundations and the footings in place. At several locations the ledge will serve as the footing. The rock will be drilled, rebar set and the foundation tied to the rock according to methods approved by the structural engineer and the building inspector.