Monday, August 24, 2009
Work continues of footings and foundation walls this week, with the goal, weather permitting, of completing foundation walls by the end of the week.
Next week, foundation insulation will be put into place and the walls backfilled. Then excavation will begin in the slab area to establish proper grades in preparation for the sub-slab plumbing.
Your building committee continues to meet weekly on Thursday evenings with the architects and the contractors. The professional team meets regularly on Monday mornings at the job site.
Photos show the preparation for the foundation wall pours.