Foundations completed.




Foundations were completed on Friday, August 28. Insulation is being put in place on the outside of the foundation walls down to the footings and will be backfilled this week.

On the interior of the foundation walls the soil is being compacted. The drain pipes that serve the kitchen, bathrooms, and janitor’s closet will be positioned, along with the piping for the radon remediation system. Stone will be placed on top of the compacted soil. Insulation will be placed upon the stone layer. Once all is in proper position, next week the concrete grade beams and slab will be poured.