Thursday, November 5, 2009

Update for November 5

Thanks to Rick High for this update as of Thursday Nov. 5:

Work is progressing on many fronts.
The site contractor has tied into the water line in Elm Street and is
working his way back toward the new building. He has encountered what
appears to be 30 feet or so of ledge, which will be drilled and fractured so
it can be removed.
The septic system is now competed and awaiting final sign-offs from the
inspectors.
All windows are now installed in the building and by tomorrow all roofing
will be complete. Exterior trim work is proceeding with soffits being
installed. The "fins" and light shelves are following. Siding is scheduled
to start next week.
Inside the flooring contractor is completing the work of grinding and
finishing the concrete into the final floor. This will then be covered with
a protective layer to avoid any damage while work proceeds inside. Interior
framing will begin next week.
The electricians have brought temporary electric power to the building.
Electrical work, plumbing and the heating and ventilation system will follow
the interior partitioning.