Monday, January 11, 2010

Paint on the walls but waiting for electric company

Finish work continues apace in the Fellowship Building.

The first coat of paint is complete. Tile has been installed in the restrooms. Fire alarms and strobe lights are in and lighting fixtures are being installed. Wood trim is underway in the community room. The grid for the dropped ceiling is being installed and nearing completion. Cabinetry and shelving is in place in the classrooms. Mechanical equipment for heating, ventilating and hot water is in place.

Plumbing fixtures will be installed later this week. The acoustic coating for the ceiling in the main hall will be applied this week. Interior doors will arrive shortly and be installed.

Our biggest current challenge is getting permanent power to the building and we are working on a daily basis to get National Grid to complete this work as we can’t start up the mechanical equipment until this happens.