From Rick High:
We have a few odds and ends of things to work on, but the building is essentially complete and awaiting the arrival of utilities. We are working daily with National Grid to get service just as soon as possible. The delivery of power will allow the start up of the building’s heating and ventilating system.
We are about 85% complete on site work, and most of the rest of the site work will need to wait until the spring thaw.
We are working on fitting up the kitchen. The vent hood was installed last week. Counters, plumbing fixtures, and appliances should arrive next week,
Other remaining items are “punch list” items”: paint touch up, a broken pane of glass or two that need to be replaced, etc.