Who would have thought an electric meter could be such a pretty sight? It was installed Tuesday afternoon.
On Thursday, CMGC’s electric subcontractor will come into the building and begin the conversion from temporary power to permanent power. This should be completed by Monday. We have asked National Grid to schedule removal of the old wires back to Elm Street for Tuesday. They have not yet responded to our request. We will move forward with Charter, Verizon and the municipal fire circuit as soon as the old wires have been removed.
Bill DiBurro has called for the gas meter to be installed and we hope that can happen tomorrow. As soon as gas is available to the building, we can fire up the heating and ventilating system and dismantle the temporary heat.
Meanwhile, work in the kitchen is progressing.