August 12, 2009
Work continues this week on the septic system and on the foundation. The new leaching field has been inspected and filled with sand. Pipe will be laid this week and the septic tank installed.
Excavation for the foundation is stalled for the moment with some significant ledge in the way that cannot be handled by the large equipment. Blasting will be necessary in two locations, and a subcontractor has been engaged. Meanwhile, the foundation subcontractor will begin setting forms today on the worship hall wing of the building. We are still working toward pouring concrete next week.
Two photos show the ledge we have encountered. The other shows the excavation for the septic tank with the sand-filled leaching field in the background.